When One Nordic faced an urgent need to replace a medium-voltage switchgear in a wind farm due to an unexpected outage, securing a quick delivery from the existing supplier proved challenging.
The fastest alternative from the original supplier had a 10-week delivery time, while an identical replacement would have taken up to 40 weeks – resulting in a major production loss for One Nordic’s end customer.
Seeking a better solution, One Nordic turned to KL Industri.
KL Industri offered their own switchgear, unerRING, which was already in stock in Finspång. Within just a few days, it was delivered and installed, significantly reducing downtime and enabling a much faster restart for One Nordic’s client.


– “We needed to replace a switchgear in a wind farm substation. In this situation, KL Industri was able to deliver the required switchgear with the right configuration immediately because they had it in stock. Unlike other suppliers, KL Industri offers a modular product that is readily available and can quickly be assembled to meet the desired configuration,” explains Isak Carlsson, project manager at One Nordic.
Carlsson also highlights the advantage of working with KL Industri as a local partner.
– “For our teams in Norrköping, the proximity to KL Industri is a real benefit,” he adds.
KL Industri takes pride in delivering high-quality products with fast lead times, helping customers meet their low- and medium-voltage switchgear needs efficiently.
For more information about KL Industri’s products and services, visit KL Industri. We are committed to supporting the local, national, and Nordic energy and industrial sectors.